10-Point Checklist for Accepting a Shared TV System Before Sign-Off

10-Point Checklist for Accepting a Shared TV System Before Sign-Off

Problems found after sign-off usually become the building's cost. Good acceptance does not require deep expertise, only knowing what to ask for and where to measure.

10-point checklist

#CheckPass when
1Outlet level65–75 dBµV on every channel at every measured outlet
2MER/BERMargin above threshold as per TOR
3Channel listMatches the TOR
4SlopeLow and high channels close in level
5LTE/5G filterInstalled before the first amplifier
6Grounding and lightning protectionAntennas, dishes and headend grounded
7Connectors and cablingCompression connectors, labelled cables
8As-built riser diagramMatches the site
9Test reportNumeric results with date, instrument and tester
10Training, warranty, MAStaff trained, warranty and contact provided

Choose the measuring points yourself, favouring the last outlet of each riser and the top floor. Do not accept reports without numbers or pre-construction drawings.